Depot safety project almost complete

A work health and safety pilot program at Central Coast Council's Woy Woy Depot is 85 per cent complete, according to an update of 2017-18 capital projects.

Councillors were told at their June 25 meeting that the project involved making "various work health and safety improvements at the Woy Woy stores and bulk yard".

The project had a $30,000 budget and was expected to be completed by June 30.

It involved installation of bulk yard access gates and a stores shopfront and removal of a non-compliant mezzanine.

"Year-to-date costs have been mis-allocated in Oracle. These are being investigated," the report said.