Construction starts on pedestrian underpass
Night construction works within the rail corridor at Woy Woy were undertaken on Saturday, September 14, and Sunday, September 15.
The works were the start of construction of the pedestrian-cycleway underpass at Rawson Rd, Woy Woy.
This is the first stage of a project to remove the existing level crossing at Rawson Rd.
The construction works were undertaken during a rail shutdown period and involved the removal of a section of rail track and the excavation of materials and installation of sheet piling across the track.
The work will allow the installation of the underpass during the next rail shutdown, which is scheduled for March next year.
Nearby residents may have experienced construction noise.
Media release, 11 Sep 2013
Gosford Council