Gosford Council has detailed a list of projects currently operating or recently begun for the week beginning October 2.

Works are located at Umina Beach, Woy Woy, Pretty Beach, Patonga, Ocean Beach, St Huberts Island, Booker Bay, Wagstaffe and Killcare Heights.

Works at Umina Beach involve the construction of a roundabout at the intersection of Ocean Beach Rd and Wellington St, and a rebuilding of the Umina Beach Surf Club.

A surf club rebuilding program is also due to commence at Ocean Beach.

Works at Woy Woy involve the construction of footpath on Ocean Beach Rd and the construction of a cycleway on the Boulevarde.

Works on St Huberts Island involve the removal of an existing playground and the construction of a new one on the corner of Solstice and Attunga Ave.

Stormwater drainage construction has commenced in Mulhall St, Wagstaffe.

At Patonga, Stage 1 works at the caravan park have been completed, with stage 2 works due for completion in October.

Works at Booker Bay involved the adjustment of footpath on Orange Grove Rd.

At the intersection of Wards Hill Rd and The Scenic Rd, Killcare, drainage works are 95 per cent complete.

Roadside restoration on Wards Hill Rd is currently in progress.

Works at Pretty Beach involved the construction of a boat ramp, and the adjustment of a sewer rising main on Como Parade.

Main cleaning by air scouring is currently in progress across the Peninsula, involving all streets from Woy Woy to Umina Beach and Booker Bay.