Killcare drain upgrade
Gosford Council will upgrade drainage in Fraser Rd, Killcare.
The works will take about eight weeks, starting late May.
About 230 metres of stormwater drainage pipes and 12.2 metres of box culverts will be installed, together with the construction of stormwater pits and associated works.
Council said that Water Sensitive Urban Design was considered for the project.
However, the nature of the Hardys Bay catchment would make it too difficult to locate the approach within this stage of the drainage system.
The approach would be considered for inclusion in future stages of the Hardys Bay catchments drainage system.
Council appointed Milibant Constructions Pty Ltd for the work.
Council Agenda COR.49, 3 May 2011