Last year's projects now due next year
A number of council works on the Peninsula that were meant to have been undertaken last financial year will not be completed until next year, Gosford Council has been told.
Gosford Council has received a report on the projects.
The council was told that a reservoir inlet valve and scour diversion at Mt Ettalong, with a combined expenditure of $73,049, are expected to be completed next year, as is another inlet valve replacement at Blackwall worth $10,000.
The Glenrock Pde stormwater, curb and guttering and pavement project, with an expenditure of $140,000, is 75 per cent complete and council officers expect it to be completed by early next year.
Woy Woy CBD paver sealing worth $12,400 is expected to be completed by February next year.
An upgrade of Ettalong Caravan Park, with a total cost of $20,000, has been given a likely completion date of June next year.
West St Umina surface drainage, expected to cost $25,000, was expected to be completed by the end of the year but was deferred for further community consultation.
Rechlorination plants at Killcare, Pretty Beach and Pearl Beach, with a combined budget of $60,000, have not yet begun.
They are expected to be completed next year.
Council agenda FS.143, November 23